The Hillside Aluminium Smelter project, Richards Bay, South Africa
.

   
Client: Alusaf Limited.
Brief: Core owner's team to expand Alusaf’s production capacity by building the 466 ktpa greenfield Hillside Smelter.
Budget: US $ 2 billion.
Construction: Expected to take 36 months, but completed in 31 months.
Technology: Pechiney AP28/30 technology.
Power Supply: Plant consumes 840 Megawatts of continuous power, equivalent to the total consumption of Cape Town and Port Elizabeth - ESKOM's largest customer by far!
Environmental considerations: Comprehensive EIA completed September 1992, including public response reports. Forerunner of most current day SA large project EIA's.
Current production: Producing 500 ktpa of aluminium ingots.
A word from the owner: It is the world’s largest greenfield aluminium smelter.



For more info visit: www.bhpbilliton.com or contact GTI.